Our work

Installed across Kerala.

A few of the homes and businesses now running on their own roof.

3 kW residential solar install in Manjeri, Malappuram
Residential

Rooftop home

Capacity
3 kW
Town
Manjeri
20 kW commercial solar install in Kottakkal, Malappuram
Commercial

Office rooftop

Capacity
20 kW
Town
Kottakkal
5 kW residential solar install in Tirur, Malappuram
Residential

Villa system

Capacity
5 kW
Town
Tirur
50 kW industrial solar install in Perinthalmanna, Malappuram
Industrial

Factory array

Capacity
50 kW
Town
Perinthalmanna

Delta

Energy in a few
numbers.

Learn more →
₹78,000

Govt subsidy, direct to your bank

up to 90%

Reduction in KSEB bill

25+

Panel performance warranty

4–7 yrs

Typical payback period

The process

From your bill to a live meter.

Going solar in Kerala means satisfying two separate authorities: KSEB, who must approve the connection and fit the meter, and the central PM Surya Ghar scheme, which pays the subsidy. They run on different portals and different paperwork. This is the whole sequence, and who does what at each stage.

  1. Your bill, and a look at the roof

    Delta

    It starts with a recent KSEB bill. It carries your consumer number, your connection type and your consumption history, which between them determine what size system makes sense and whether you are eligible for the residential subsidy at all. A site visit then settles what the bill cannot: usable area, shading through the day, roof condition and where the inverter and cabling will run.

  2. A written quote, before anything is ordered

    Delta

    You get the system size, the specific panels and inverter, the expected annual generation, the price, the subsidy you should receive and the warranty terms — in writing. Nothing is ordered and nothing is charged until you have that and have agreed to it.

  3. Registration on the national portal

    You, with us

    The PM Surya Ghar application is made against your consumer number and your bank account, so this is the step that has to be yours. We sit with you through it. The bank account you register is where the subsidy will land, so it needs to be right and it needs to match the connection holder.

  4. The KSEB application

    Delta

    All grid-interactive rooftop applications go through the Solar Rooftop Portal – Kerala. We prepare and file the connectivity application and the technical documentation for the proposed system, and handle the correspondence from there.

  5. Approval, then installation

    Delta

    Installation follows approval, not the other way round — a system commissioned early is a problem to unwind rather than a head start. The rooftop work itself is typically a few days for a domestic system: mounting structure, panels, inverter, earthing and protection, then the connection into your board.

  6. Inspection and the net meter

    KSEB

    KSEB inspects the installation against the safety and technical requirements, and on clearing it replaces your meter with a bidirectional net meter and fits the renewable energy meter. Both are installed and sealed by KSEB. From the moment they are live, your generation starts counting against your bill.

  7. The subsidy reaches your account

    Central government

    With commissioning confirmed, the central financial assistance is credited directly to the bank account on your PM Surya Ghar application — to you, not to us. Delta never receives it on your behalf, which is why the quote you signed is the amount you pay.

End to end, consultation to a live net meter typically runs 4–8 weeks. Most of that is not construction — the rooftop work is a matter of days — but approval and inspection, which run to the utility's schedule rather than ours.

What Delta does

  • Sizing the system from your consumption and your roof
  • The written quote, with named equipment and warranty terms
  • The KSEB connectivity application and technical documentation
  • Sitting with you through the PM Surya Ghar registration
  • Installation, earthing and protection
  • The test-cum-completion certificate and inspection correspondence

What we need from you

  • A recent KSEB bill to start from
  • Registering on the national portal against your own consumer number
  • A bank account in the connection holder's name for the subsidy
  • Roof access on the installation days
  • Being available when KSEB comes to inspect
Questions

About our installations.

Still unsure about something? Message us on WhatsApp and we'll answer in plain Malayalam or English.

  • Usually. We work across Malappuram district, so there is often an installation close enough to look at. Ask and we will arrange what the owner is happy for us to show.

Get a free quote

Ready to cut your KSEB bill?

Tell us a little about your home or business and we'll get back to you within 24 hours.

Mon–Sat · 9 am – 6 pm

Start your solar journey today.

Get a free quote